Section 7 Environmental Effects of the Selected Plan
EAA Storage Reservoirs Revised Draft PIR and EIS February 2006
7-26
2. Railroad Bridges - Three railroad bridges would be affected by the
increased conveyance requirements for the NNR and Miami Canals. One
railroad bridge crosses the NNR and two cross the Miami Canal. The
bridge across the NNR is owned by Florida East Coast Railway (F.E.C.
RY.). Of the two bridges across the Miami Canal, one is owned by U.S.
Sugar Corp; the second is owned by Seaboard System Railroad.
Replacement of the affected bridges will be in close coordination with the
owners and to the applicable railroad design and construction standards.
An attempt to maintain railroad traffic across the NNR and Miami Canals
will depend on rerouting shipments where possible, during the demolition
and construction of any of the impacted bridges. In the case that traffic
can not be rerouted or maintained in any other way, a temporary bridge
will be erected beside the existing bridge during the construction of the
new bridge.
3. Privately Owned Agricultural Traffic Bridges
- Nine privately owned
bridges would be affected by the increased conveyance requirement for the
NNR. Two privately owned bridges would be affected by the increased
conveyance requirement of the Miami Canal. Five privately owned
bridges will be affected by the increased conveyance requirement of the
Cross Canal. One privately owned bridge will be affected by the
conveyance requirement of the Bolles Canal. These bridges will be
replaced in kind, type and size, and meeting present day FDOT standards
and requirements. The bridges will be replaced in a manner that will
interrupt traffic for the agricultural haulers and vehicular traffic as little
as possible. There are enough bridges and they are close enough to each
other that traffic can be rerouted. Traffic on the levees along the canal
banks is an everyday event and we do not foresee problems with rerouting
traffic through other bridges while others are being replaced.
4. Pump Station Intake Structures and Other Control Structures - There are
many of these categories of structures that will need to be replaced due to
the canal improvement work. Each structure will be replaced with the
same type, capacity and operationally sound structure. Interim pumps
will be provided for critical water supply canals during normal flow
interruption.
7.20.2 Utility Re-Alignments
Utility relocation is anticipated in conjunction with the replacement of two
bridges. Fiber optic communication lines are attached to one bridge, and a water
main to the other. Relocation of utilities attached to bridges will be included as
part of the bridge construction project. A high voltage electrical transmission
line, and an aerial electrical distribution line and telephone line will also require
relocation due to canal improvements near Lake Okeechobee. Relocation of an
overhead electrical distribution line and telephone line that crosses through the