
Section 5 Formulation of Alternative Plans
EAA Storage Reservoirs Revised Draft PIR and EIS February 2006
5-19
FIGURE 5-6: TYPICAL RCC LEVEE SECTION
Currently, the total construction cost estimates are within approximately 7% for
both the earthen and RCC embankments. Design assumptions and
requirements have been refined based upon the results of a project recently
constructed and operated by the SFWMD. The objectives of this project, called
“Temporary Test Embankment Cell Construction,” were to: 1) obtain
performance data on the seepage potential at the reservoir site, 2) evaluate the
suitability of on-site materials for embankment construction and slope
protection, and, 3) determine the suitability of cap rock for chimney and drain
materials.
5.3.2.2 Cut-off Wall
Based on the preliminary evaluation of embankment stability and potential off-
site impacts, cut-off walls will be needed for the EAA reservoirs. The cut-off wall
would ensure that off-site impacts are within acceptable limits and that exit
gradients have adequate safety factors against potential piping failure. For
earthen embankments, it is estimated that a 35 feet cut off wall will be needed
along the east side (US-27), north and west sides (agricultural areas), and along
STA 3/4 side in the south. Along the Holey land area to the southwest, a 50-foot
deep cut-off wall is recommended. For the roller compacted concrete
embankment, a 50-foot deep cut-off wall is recommended along the entire
reservoir perimeter. The cut-off wall will be composed of soil-bentonite mix with
a minimum width of 3 feet. The cut-off wall evaluation is presented in details in
the Engineering Appendix.
Komentarze do niniejszej Instrukcji