Section 6 The Selected Alternative Plan
EAA Storage Reservoirs Revised Draft PIR and EIS February 2006
6-16
until the first of the month following the estimated construction completion date.
Interest during construction is shown within Table 6-7.
TABLE 6-7: TOTAL INTEREST DURING CONSTRUCTION
COST COMPONENT
Construction Features $832,761,089
Real Estate $80,134,000
Total Initial Cost $912,895,089
Interest During Construction
IDC Construction $77,244,499
IDC Real Estate $16,518,781
IDC Recreation $31,766
Total Interest During Construction $93,795,046
The cost of a project is the investment incurred up to the beginning of the period
of analysis. The investment cost at that time is the sum of construction and
other initial cost such as real estate and PED cost plus interest during
construction. The IDC for the construction element of the selected alternative
plan is $77,244,499.
Interest during construction was computed for real estate using the date the
lands are to be certified for the project. The total IDC on real estate is estimated
to be $16,518,781. The average annual water quality monitoring costs are
estimated to be $350,000 (see Annex F).
6.2.3 Operation, Maintenance, Repair, Replacement, and Rehabilitation Costs
Annual operation and maintenance costs were estimated for the construction
features of the selected alternative plan. The operation and maintenance costs
were determined by extrapolation from operational cost histories supplied by the
SFWMD, by using industry standard cost data and by using data from past and
projected future cost trends. The average annual operation, maintenance,
repair, replacement and rehabilitation (OMRR&R) costs are estimated to be
$2,413,982 (Table 6-8).